My city building department just called. My plans for a detached 18x28 garage/workshop have made it through plan check and have been approved by the planning department. I should be able to pull the permit tomorrow.
Now is my last chance to specify the "must haves" before finalizing the contract with my contractor of choice.
Basic features now:
18 x 28, 2x6 exterior framing, 2-coat stucco over R-Tech foam, 30-year dimensional comp shingles (largest structure to still be in scale with house and not crowd access to the rest of the lot.)
Flat floor (to have a polyaspartic coating)
12 x 8 door, probably a roll up but could be an insulated sectional door.
Insulated walls (R24) and ceiling (R32).
Vaulted ceiling.
All interior walls and ceiling drywalled.
6' sliding patIo door and 6' x 4' window on one side
four 4' x 1' horizontal windows under eve on opposite side;
35 amp 110 + 220 electrical service
sink and toilet
tankless water heater
What "must haves" have I omitted?
One area that I know I must address is heating and cooling. It is 100* for about 100 straight days every summer, with some weeks over 110*. Winter is 40's and high 30's with an occasional freeze. I could put a swamp cooler in the roof but I know there are more high tech solutions for in wall and ductless units. Suggestions?
BTW - I am having the slab poured with a potential future lift in mind but have no immediate plans for a lift. This is going to be more of a man cave/tinkerer's paradise than a fabrication shop.
Now is my last chance to specify the "must haves" before finalizing the contract with my contractor of choice.
Basic features now:
18 x 28, 2x6 exterior framing, 2-coat stucco over R-Tech foam, 30-year dimensional comp shingles (largest structure to still be in scale with house and not crowd access to the rest of the lot.)
Flat floor (to have a polyaspartic coating)
12 x 8 door, probably a roll up but could be an insulated sectional door.
Insulated walls (R24) and ceiling (R32).
Vaulted ceiling.
All interior walls and ceiling drywalled.
6' sliding patIo door and 6' x 4' window on one side
four 4' x 1' horizontal windows under eve on opposite side;
35 amp 110 + 220 electrical service
sink and toilet
tankless water heater
What "must haves" have I omitted?
One area that I know I must address is heating and cooling. It is 100* for about 100 straight days every summer, with some weeks over 110*. Winter is 40's and high 30's with an occasional freeze. I could put a swamp cooler in the roof but I know there are more high tech solutions for in wall and ductless units. Suggestions?
BTW - I am having the slab poured with a potential future lift in mind but have no immediate plans for a lift. This is going to be more of a man cave/tinkerer's paradise than a fabrication shop.