I'm a maintenance freak since the Navy introduced me to PMS system. I've been struggling to get a maintenance schedule set up for my Airstream and associated gear.
So, I jumped out to Grok, got into chat mode and started asking questions. The results look great!
Here's an example:
Periodicity: A (Annually) + monthly visual
Safety/PPE: Gloves; no open flame; ventilate
Tools & Supplies: Soapy water solution, spray bottle, flashlight
Steps:
Note that even the data sources are referenced.
AI just compressed six months worth of work compiling and formatting into an afternoon of messing about on a computer. It will actually take longer to verify this information than to generate the individual PMS Cards.
So, I jumped out to Grok, got into chat mode and started asking questions. The results look great!
Here's an example:
Card 9: LP Gas System – Visual & Bubble Test
Equipment/System: Propane Tanks, Regulator, LinesPeriodicity: A (Annually) + monthly visual
Safety/PPE: Gloves; no open flame; ventilate
Tools & Supplies: Soapy water solution, spray bottle, flashlight
Steps:
- Open propane cover; close tank valves.
- Inspect tanks, pigtails, regulator, main line for cracks/damage.
- Open one tank valve; sniff test fittings.
- Apply soapy water to all connections (regulator, pigtails, appliance inlets)—watch for bubbles.
- Exercise appliances briefly (blue flame only).
- Close valves when finished.
Note that even the data sources are referenced.
AI just compressed six months worth of work compiling and formatting into an afternoon of messing about on a computer. It will actually take longer to verify this information than to generate the individual PMS Cards.